SAA PROJECT
STATION EXTINTION MAJNOON
1. Installation, testing, and operation of 11kV SWICHGARE and 11LV\400V transformer.
2. Installation, testing, and operation of water pumps.
3. Installation, testing, and operation of DC110V system and instrument devices.
4. Construction of a pump room.
5. Extension of all high-voltage and control cables.
6. Extension of all instruments cables.
Road Maintenance
Road Maintenance for OHTL 33KV
1- Land modification and leveling
2.Geogrid installation
3. Sub-base layer installation
4. Stone layer spreading
5. Compaction (rolling)
6. Final delivery
MAJNOON BRIDGE GATE
Design and packaging of Majnoon Field Gate
The gate should incorporate a modern and appealing design that harmonizes with the environment
Engineers and designers consider environmental and sustainability aspects when designing and encasing the gate.
The construction and installation of the gate be carried out with precision and high professionalism to ensure a long life and optimal performance.
DS2-EHOUSE Project
DS2-EHOUSE Power Station Expansion Project
1- Switchgear Panel Installation: Install a new switchgear panel.
2- Cable Laying and Trenching: - Trench digging for cable installation. - Laying, connecting, and testing power cables, fiber optic cables, and control cables.
3- Testing and Commissioning: - Comprehensive system testing and commissioning.
4- Electrical Component Testing: - Testing CT & PT. - Testing protection relay. - Testing DC contact. - Megger and hi-pot testing. - Settings and configuration.
WASTE MANAGEMENT - INCINERATOR AND LANDFILL PROJECT
Inspection and commissioning of the waste incinerator in collaboration with Al-Yamama Engineering Company.
Waste incinerator inspection and operation conducted efficiently.
PLC installed for automated control of processes.
SCADA system implemented for real-time monitoring and control.
Assessment Fire and alarm system installed for safety measures.
WASTE MANAGEMENT - INCINERATOR AND LANDFILL PROJECT
Inspection and commissioning of the waste incinerator in collaboration with Al-Yamama Engineering Company.
Waste incinerator inspection and operation conducted efficiently.
PLC installed for automated control of processes.
SCADA system implemented for real-time monitoring and control.
Assessment Fire and alarm system installed for safety measures.