photo_2024 08 03_14 36 45 2 1 e1763740264469

DS2-E-House Power Station Expansion Project

A project to expand the DS2 E-House power distribution station by installing new switchgear, power and control cables, and fiber-optic systems. Works included excavation, cable trenching, and full testing and commissioning. The upgrade enhances power reliability and increases load capacity within the facility. The project reflects ECD’s expertise in medium-voltage systems and integrated electrical works.

photo_2024 05 17_22 45 49 e1763740368323

SAA – Station Extension at Majnoon Oilfield

The project covers the extension of the station by installing 11 kV switchgear, 11 kV/400 V transformers, water-pumping systems, and a DC110V control system. Scope included high-voltage, control, and instrument cabling. A dedicated pump room was constructed to support utility services. The project ensures improved operational capacity for field facilities.

photo_2024 05 24_22 33 03 e1763740539835

Waste Management – Incinerator & Landfill System

A complete inspection, commissioning, and activation of a waste management system including incinerators and landfill units. The project incorporated PLC-based control, SCADA monitoring, and full fire and alarm protection systems. It ensures environmentally safe waste processing for industrial operations. Delivered in collaboration with Al-Yamama Engineering.

صورة واتساب بتاريخ 2024 05 17 في 23.26.29_19ba703d e1763751409776

Majnoon Bridge Gate Project

Design and construction of the main gate structure for the Majnoon Oilfield Bridge. The project focused on delivering an aesthetically modern and durable entrance structure. Materials and fabrication were selected to match harsh environmental conditions. The final installation enhances the identity and appearance of the field facilities.

photo_2024 07 05_11 29 09 2 e1763751496202

Road Maintenance for 33 kV OHTL Access

Maintenance and rehabilitation of access roads serving the 33 kV overhead transmission line. Works included leveling, geogrid installation, sub-base layers, gravel placement, and final compaction. The restored road ensures safe access for construction and maintenance teams. The project improves long-term stability and mobility along the transmission route.

صورة واتساب بتاريخ 2025 02 12 في 23.24.08_9ca93455 e1763751671903

OHTL 33 kV – DS2 to WIP

Construction of a 33 kV overhead transmission line from DS2 to WIP. The scope included pile breaking for old foundations, new foundation casting, and tower installation works. The project improves electrical connectivity between key facilities in the Majnoon field. ECD delivered structural, civil, and electrical works with high precision.

photo_2024 07 05_13 58 09 e1763751770822

Solar Power System – ECD Camp, Majnoon Oilfield

Installation of the first solar-energy system at the ECD camp using high-efficiency photovoltaic panels. The system provides continuous clean power and reduces reliance on diesel generators. It supports sustainability goals and lowers operational energy costs. The project highlights ECD’s capability in renewable-energy deployment.

photo_2025 11 01_00 03 56 1 e1763753554480

PC Power System Upgrade Project

A comprehensive upgrade of the PC power system, involving new 11 kV cable routing from DS2 GTG to the PC Extension, from PC Extension to PC Annex, and from PC Extension to the PC Substation. The scope included the installation of two 11 kV transformers, new switchgear units, and RMUs. Full testing and commissioning were performed to ensure system integrity, protection coordination, and reliable load transfer. The upgrade significantly enhances power distribution capacity and operational stability across the PC facilities.

صورة واتساب بتاريخ 2025 11 04 في 14.28.40_3f8e8c6a e1763753890553

Pipeline Installation at TPS – CPF2

The project involved installing a new pipeline inside the TPS area at CPF2, including routing, welding, and structural support works. All joints underwent full NDT inspection, including RT and PT evaluations, to ensure weld integrity. A complete hydrostatic (hydro) test was performed to verify pressure performance and system safety. The project enhanced the pipeline network’s reliability and operational readiness within the CPF2 facilities.

2 2 e1763754088847

New Warehouse & Pipe Yard Extension – Lot 4 Project

A major yard-expansion project that included preparing a large soil platform with full sub-base layers, gravel leveling, and compaction to meet industrial load requirements. The scope also covered the construction of a new asphalt access road to support vehicle and equipment movement. A high-standard perimeter protection fence was installed to secure the warehouse and pipe storage area. The upgraded yard provides increased storage capacity, safer logistics flow, and improved infrastructure for ongoing field operations.

photo_2025 10 31_13 59 39 e1763754189416

33 kV OHTL Northwest Loop – Phase 1 & Phase 2 (DS2 GTG to CPF2)

An EPC project covering the construction of a 33 kV overhead transmission line forming the Northwest Loop from DS2 GTG to CPF2. The scope included tower foundation works, tower erection, and full road maintenance along the OHTL route. The project also involved the installation of 33 kV switchgear and laying medium-voltage power cables to complete the loop. This system upgrade enhances network reliability, improves power distribution stability, and supports future load expansion across the field facilities.

5 1 e1763754282910

11 kV Cable Replacement Project

A complete cable replacement project involving excavation of a 1.5 km (1500 m) cable trench from DS2 Substation to the FOC facility. The scope included laying three new 11 kV power cables, backfilling, route marking, and providing full protection measures along the trench. All cables underwent comprehensive testing and commissioning to ensure proper insulation, continuity, and load performance. The upgrade enhances system reliability and restores safe, stable power delivery to the connected facilities.

صورة واتساب بتاريخ 2025 11 21 في 22.48.02_16a7f3b4 e1763758681398

Louver Installation & Gas Detector Relocation Project

(Executed in collaboration with Wood) A field-wide upgrade project involving the installation of industrial louvers inside battery rooms across 16 wellpads in the Majnoon Oilfield. The scope included modifying ventilation openings, installing louver assemblies, and ensuring proper airflow and heat-dissipation performance. Gas detectors (CH₄ and H₂S) were relocated and recalibrated to meet updated safety and ventilation requirements. The works were executed in coordination with Wood to ensure full compliance with HSE standards and site specifications, enhancing the overall safety and reliability of wellpad operations.